Time and Work Notes: Short Tricks To Solve Questions

Time and Work Notes: Short Tricks To Solve time & work questions

Time and work is an important topic for various competitive examinations such as Banking, SSC, railways and other examinations. A stronghold on this topic will definitely help you to ace the exam with flying colours. Learn about the formula and short tricks to solve the Time and work questions. Get time and work questions with answers given below. The time and work questions are the foundation to various other concepts including Data interpretation, and Data sufficiency.

Time And Work Formula & Tricks

Time= Work done/Efficiency
  • When work is same.
 Time∝1/Efficiency
  • If A can do a piece of work in n days.
                                               Then, per day working efficiency of A = 1/n
  • If working efficiency of A & B is → x : y.
Then, the time taken by A & B to finish the work is in the ratio → y : x
e.g. If A does three times faster work than ‘B’, then the ratio of work done by A and B is 3: 1.
                Then, Ratio of time taken by A & B = 1 : 3
  • If A can do a piece of work is x days and B can do a piece of work in y days, then both of them working together will do the same work in
xy/(x+y)  days
Explanation 
⇒ A’s 1 day’s work = 1/x
B’s 1 day’s work = 1/y
(A + B)’s 1 day work = 1/x+1/y =(x + y)/xy
A + B will complete the work in = xy/(x + y)

Q. A can finish a piece of work by working alone in 6 days and B, while working alone, can finish the same work in 12 days. If both of them work together, then in how many days, the work will be finished? 
Sol.  x = 6, y = 12
Working together A + B will complete the work in = xy/(x + y)=(6 × 8)/18
= 4 days
  • If A, B & C will working alone, can complete a work in x, y and z days, respectively, then they will together complete the work in
xyz/(xy+yz+zx)
Explanation
⇒ A’s 1 day work = 1/x
B’s 1 day work = 1/y
C’s 1 day work = 1/z
(A + B + C)’s 1 day work = 1/x+1/y+1/z  =(yz+xz+xy)/xyz
(A + B + C) will complete the work in
=xyz/(yz+xz+xy)

 

Q. A, B, and C can complete a piece of work in 10, 15 and 18 days, respectively. In how many days would all of them complete the same work working together?
Sol. x = 10 days, y = 15 days & z = 18 days
The work will be completed in
=(10×15×18)/(10×15+15×18+18×10)
=2700/600=4½  days
  • Two persons A & B, working together, can complete a piece of work in x days. If A, working alone, can complete the work in y days, then B, working alone, will complete the work in
⇒xy/(y-x)
Explanation 
⇒ A + B’s 1 day work = 1/x
A’s 1-day work = 1/y
B’s 1 day work = 1/x-1/y
=(y-x)/yx
B will complete the work = yx/(y – x)

 

Q. A and B working together take 15 days to complete a piece of work. If A alone can do this work in 20 days, how long would B take to complete the same work?
Sol. x = 15, y = 20
B will complete the work in = (15 × 20)/5
= 60 days

Click Here to Attempt More Questions From Quantitative Aptitude For SSC CGL 

  • If A & B working together, can finish a piece of work is x days, B & C in y days, C & A in z days. Then, A + B + C working together will finish the job is
⇒2xyz/(xy+yz+zx)
Explanation
⇒ A + B’s 1 day work = 1/x
B + C’s 1 day work = 1/y
C + A’s 1 day work = 1/z
[(A + B) + (B + C) + (C + A)]’s 1 day’s work
=1/x+1/y+1/z
=(yz+xz+xy)/xyz
2 (A + B + C)’s 1 day work = (xy + yz + xz)/xyz
A + B + C’s 1 day work = (xy + yz + xz)/2xyz
A + B + C working together will complete the work in
=2xyz/(xy+yz+xz)

 

Q. A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. How long would they take to complete the full work together?
Sol. x = 12 days, y = 15 days, z = 20 days
A+B+C=(2×12×15×20)/(180+300+240)
=7200/720=10 days
  • If A can finish a work in x days and B is k times efficient than A, then the time taken by both A and B, working together to complete the work is
x/(1+k)
Explanation
⇒ Ratio of working efficiency, A & B = 1 : k
Ratio of Time taken = k : 1
k → x days
1r → x/k days
A → x days
B → x/k days
1 day work of A = 1/x
1 day work of B = k/x days
(A + B)’s 1 day work = 1/x+k/x=(k + 1)/x
(A + B) will complete the work is = x/(k+1)

 

Q. Harbans Lal can do a piece of work in 24 days. If Bansi Lal works twice as fast as Harbans Lal, how long would they take to finish the work working together?
Sol. x = 24, k = 2
Working together they will complete the work in = 24/(1 + 2)
=24/3=8 days

 

  • If A & B working together can finish a work in x days & B is k times efficient than A, then the time taken by,
A working Alone will take ⇒ (k + 1) x
B working Alone will take ⇒ ((k+1)/k)x
Explanation
⇒ Efficiency Ratio → 1 : k
Time Ratio → k : 1
A’s 1 day work = 1/k
B’s 1 day work = 1
(A + B)’s 1 day work = 1/x
1/k+1=1/x
(k+1)/k=1/x
k = (k + 1) x
A alone working together will take ⇒ (k + 1) x days
1 ratio = ((k + 1) x)/k
B Alone working Alone will take
⇒((k + 1) x)/k

 

Q. A and B together can do a piece of work in 3 days. If A does thrice as much work as B in a given time, find how long A alone would take to do the work?
Sol. x = 3, k = 3
Time taken by A, working Alone to complete the work = ((3 + 1)/3) × 3 = 4 days
  • If A working Alone takes a days more than A & B,  & B working Alone takes b days more than A & B. Then ,
Number of days, taken by A & B working together to finish a job is = √ab
Explanation :
⇒ Let A + B takes x days
A → x + a days
B → x + b days
1/(x+a)+1/(x+b)=1/x
(2x+a+b)/(x²+xa+xb+ab)=1/x
2x² + xa + xb = x² + xa + xb + ab
x² = ab
x = √ab days

 

Q. A alone would take 8 hrs more to complete the job than if both A and B worked together. If B worked alone, he took 41/2 hrs more to complete the job than A and B worked together. What time would they take if both A and B worked together?
Sol. a = 8, b = 9/2
A + B will take = √(8×9/2)
=√36
= 6 days

 

Click here for more Maths Study Notes

June Current Affairs PDF

×

Download success!

Thanks for downloading the guide. For similar guides, free study material, quizzes, videos and job alerts you can download the Adda247 app from play store.

Thank You, Your details have been submitted we will get back to you.

Leave a comment

Your email address will not be published. Required fields are marked *

Join India's largest learning destination

What You Will get ?

  • Job Alerts
  • Daily Quizzes
  • Subject-Wise Quizzes
  • Current Affairs
  • Previous year question papers
  • Doubt Solving session

Login

OR

Forgot Password?

Join India's largest learning destination

What You Will get ?

  • Job Alerts
  • Daily Quizzes
  • Subject-Wise Quizzes
  • Current Affairs
  • Previous year question papers
  • Doubt Solving session

Sign Up

OR
Join India's largest learning destination

What You Will get ?

  • Job Alerts
  • Daily Quizzes
  • Subject-Wise Quizzes
  • Current Affairs
  • Previous year question papers
  • Doubt Solving session

Forgot Password

Enter the email address associated with your account, and we'll email you an OTP to verify it's you.


Join India's largest learning destination

What You Will get ?

  • Job Alerts
  • Daily Quizzes
  • Subject-Wise Quizzes
  • Current Affairs
  • Previous year question papers
  • Doubt Solving session

Enter OTP

Please enter the OTP sent to
/6


Did not recive OTP?

Resend in 60s

Join India's largest learning destination

What You Will get ?

  • Job Alerts
  • Daily Quizzes
  • Subject-Wise Quizzes
  • Current Affairs
  • Previous year question papers
  • Doubt Solving session

Change Password



Join India's largest learning destination

What You Will get ?

  • Job Alerts
  • Daily Quizzes
  • Subject-Wise Quizzes
  • Current Affairs
  • Previous year question papers
  • Doubt Solving session

Almost there

Please enter your phone no. to proceed
+91

Join India's largest learning destination

What You Will get ?

  • Job Alerts
  • Daily Quizzes
  • Subject-Wise Quizzes
  • Current Affairs
  • Previous year question papers
  • Doubt Solving session

Enter OTP

Please enter the OTP sent to Edit Number


Did not recive OTP?

Resend 60

By skipping this step you will not recieve any free content avalaible on adda247, also you will miss onto notification and job alerts

Are you sure you want to skip this step?

By skipping this step you will not recieve any free content avalaible on adda247, also you will miss onto notification and job alerts

Are you sure you want to skip this step?