Latest SSC jobs   »   Time and Work Notes   »   Time and Work Notes

Time and Work Notes, Simple Tricks To Solve Questions

Time and Work

Time and work are important topics for various competitive examinations such as Banking, SSC, railways, and other examinations. Time and Work is the most common topic which is asked in the Government exams. A stronghold on this topic will help you to ace the exam with flying colors. Learn about the formula and short tricks to solve the Time and work questions. Get time and work questions with answers given below. The time and work questions are the foundation of various other concepts including Data interpretation, and Data sufficiency.

Time & Work- Importance

There are many types of questions that are asked on the topic of Time &Work though the concept of Time & Work remains the same. It is the most common topic which is asked in every Government Exam. Candidates can expect to see Time & Work questions in data sufficiency and data interpretation also for which it becomes crucial to understand the basic concept of Time & Work. So, in this article, we have covered the Time and Work formulas as well as Time and Work Tricks so that candidates can score more marks in less time.

Time And Work Formulas & Tricks

When you know Time and Work formula, you can completely link that formula to the solution as soon as you read the question. Knowing Time & Work tricks will also help you solve the questions in a few seconds and thus saving your time for other sections. You can find Time & Work formulas along with important Time & Work Tricks below.

  • When work is the same.
 Time∝1/Efficiency
  • If A can do a piece of work in n days.
                                               Then, per day working efficiency of A = 1/n
  • If the working efficiency of A & B is → x: y.
Then, the time taken by A & B to finish the work is in the ratio → y: x
e.g. If A does three times faster work than ‘B’, then the ratio of work done by A and B is 3: 1.
                Then, the ratio of time taken by A & B = 1 : 3
  • If A can do a piece of work in x days and B can do a piece of work in y days, then both of them working together will do the same work in
XY/(x+y)  days
Explanation 
⇒ A’s 1 day’s work = 1/x
B’s 1 day’s work = 1/y
(A + B)’s 1 day work = 1/x+1/y =(x + y)/xy
A + B will complete the work in = XY/(x + y)
Q. A can finish a piece of work by working alone in 6 days and B, while working alone, can finish the same work in 12 days. If both of them work together, then in how many days, the work will be finished? 
Sol.  x = 6, y = 12
Working together A + B will complete the work in = XY/(x + y)=(6 × 8)/18
= 4 days
  • If A, B & C will work alone and can complete a work in x, y, and z days, respectively, then they will together complete the work in
XYZ/(xy+yz+zx)
Explanation
⇒ A’s 1 day of work = 1/x
B’s 1-day work = 1/y
C’s 1-day work = 1/z
(A + B + C)’s 1 day work = 1/x+1/y+1/z  =(yz+xz+xy)/xyz
(A + B + C) will complete the work in
=xyz/(yz+xz+xy)

 

Q. A, B, and C can complete a piece of work in 10, 15, and 18 days, respectively. In how many days would all of them complete the same work working together?
Sol. x = 10 days, y = 15 days & z = 18 days
The work will be completed in
=(10×15×18)/(10×15+15×18+18×10)
=2700/600=4½  days
  • Two persons A & B, working together, can complete a piece of work in x days. If A, working alone, can complete the work in y days, then B, working alone, will complete the work in
⇒xy/(y-x)
Explanation 
⇒ A + B’s 1 day work = 1/x
A’s 1-day work = 1/y
B’s 1 day work = 1/x-1/y
=(y-x)/yx
B will complete the work = yx/(y – x)

 

Q. A and B working together take 15 days to complete a piece of work. If A alone can do this work in 20 days, how long would B take to complete the same work?
Sol. x = 15, y = 20
B will complete the work in = (15 × 20)/5
= 60 days

Click Here to Attempt More Questions From Quantitative Aptitude For SSC CGL 

  • If A & B working together can finish a piece of work in x days, B & C in y days, C & A in z days. Then, A + B + C working together will finish the job is
⇒2xyz/(xy+yz+zx)
Explanation
⇒ A + B’s 1 day work = 1/x
B + C’s 1 day work = 1/y
C + A’s 1 day work = 1/z
[(A + B) + (B + C) + (C + A)]’s 1 day’s work
=1/x+1/y+1/z
=(yz+xz+xy)/XYZ
2 (A + B + C)’s 1 day work = (xy + yz + xz)/XYZ
A + B + C’s 1 day work = (xy + yz + xz)/2xyz
A + B + C working together will complete the work in
=2xyz/(xy+yz+xz)

 

Q. A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. How long would they take to complete the full work together?
Sol. x = 12 days, y = 15 days, z = 20 days
A+B+C=(2×12×15×20)/(180+300+240)
=7200/720=10 days
  • If A can finish a work in x days and B is k times more efficient than A, then the time taken by both A and B, working together to complete the work is
x/(1+k)
Explanation
⇒ Ratio of working efficiency, A & B = 1: k
The ratio of Time taken = k: 1
k → x days
1r → x/k days
A → x days
B → x/k days
1-day work of A = 1/x
1-day work of B = k/x days
(A + B)’s 1 day work = 1/x+k/x=(k + 1)/x
(A + B) will complete the work is = x/(k+1)

 

Q. Harbans Lal can do a piece of work in 24 days. If Bansi Lal works twice as fast as Harbans Lal, how long would it take to finish the work working together?
Sol. x = 24, k = 2
Working together they will complete the work in = 24/(1 + 2)
=24/3=8 days

 

  • If A & B working together can finish a work in x days & B is k times more efficient than A, then the time taken by,
Working Alone will take ⇒ (k + 1) x
B working Alone will take ⇒ ((k+1)/k)x
Explanation
⇒ Efficiency Ratio → 1: k
Time Ratio → k: 1
A’s 1-day work = 1/k
B’s 1-day work = 1
(A + B)’s 1 day work = 1/x
1/k+1=1/x
(k+1)/k=1/x
k = (k + 1) x
An alone working together will take ⇒ (k + 1) x days
1 ratio = ((k + 1) x)/k
B Alone working Alone will take
⇒((k + 1) x)/k

 

Q. A and B together can do a piece of work in 3 days. If A does thrice as much work as B in a given time, find how long A alone would take to do the work.
Sol. x = 3, k = 3
Time taken by A, working Alone to complete the work = ((3 + 1)/3) × 3 = 4 days
  • If A working Alone takes a day more than A & B,  & B working Alone takes b-days more than A & B. Then,
The number of days, taken by A & B working together to finish a job is = √ab
Explanation :
⇒ Let A + B takes x days
A → x + a days
B → x + bdays
1/(x+a)+1/(x+b)=1/x
(2x+a+b)/(x²+xa+xb+ab)=1/x
2x² + xa + BX = x² + xa + xb + ab
x² = ab
x = √ab days

 

Q. An alone would take 8 hrs more to complete the job than if both A and B worked together. If B worked alone, he took 41/2 hrs more to complete the job than A and B worked together. What time would they take if both A and B worked together?
Sol. a = 8, b = 9/2
A + B will take = √(8×9/2)
=√36
= 6 days
Q. 4 men and 5 boys can do a piece of work in 20 days while 5 men and 4 boys can do the same work in 16 days. In how many days can 4 men and 3 boys do the same work?
a. 10 days
b. 15 days
c. 20 days
d. 25 days

Correct answer:(c)

Sol: Assume 1 man’s 1 day work = x & 1 boy’s 1 day work = y
From the given data, we can generate the equations as : 4x + 5y = 1/20 —(1) & 5x + 4y = 1/16 —(2)
By solving the simultaneous equations (1) & (2),
x = 1/ 80 & y = 0

Therefore, (4 men + 3 boys ) 1 day work = 4 x 1 + 3 x 0 = 1
80 20
Thus, 4 men and 3 boys can finish the work in 20 days.

Q. Sonal and Preeti started working on a project and they can complete the project in 30 days. Sonal worked for 16 days and Preeti completed the remaining work in 44 days. How many days would Preeti have taken to complete the entire project all by herself? 

  1. 20 days
  2. 25 days
  3. 55 days
  4. 46 days
  5. 60 days

Correct answer: 60 days

Sol: Let the work done by Sonal in 1 day be x
Let the work done by Preeti in 1 day be y
Then, x+y = 1/30 ——— (1)
⇒ 16x + 44y = 1  ——— (2)
Solving equations (1) and (2),
x = 1/60
y = 1/60
Thus, Preeti can complete the entire work in 60 days

Q. P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both p and Q work together, working 8 hours a day, in how many days can they complete the work?

Correct Answer:  60/11

Sol: P can complete the work in (12 x 8) hrs = 96 hrs
Q can complete the work in (8 x 10) hrs=80 hrs
Therefore, P’s 1 hour work=1/96   and Q’s 1-hour work= 1/80
(P+Q)’s 1 hour’s work =(1/96) + (1/80) = 11/480. So both P and Q will finish the work in 480/11 hrs
Therefore, Number of days of 8 hours each = (480/11) x (1/8) = 60/11

Q. (x-2) men can do a piece of work in x days and (x+7) men can do 75% of the same work in (x-10)days. Then in how many days can (x+10) men finish the work?

Correct Answer:  12 days
Sol: 34×(x2)x=(x+7)(x10)34×(x-2)x=(x+7)(x-10)
x26x280=0⇒x2-6x-280 =0
=> x= 20   and   x=-14
so, the acceptable value is x=20
Therefore, Total work =(x-2)x = 18 x 20 =360 unit
Now   360 = 30 x k
=> k=12 days

Q. A is thrice efficient as B and C is twice as efficient as B. what is the ratio of several days taken by A, B, and C, when they work individually?

Correct Answer: 2:6:3

Sol:

A:    B:    C

The ratio of efficiency is 3:    1:    2

The ratio of No.of days            1/3:   1/1:   1/2

or                                       2:    6    :    3

Hence A is correct.

Time and Work FAQs

Q. How is Time-related to Work?

Ans: Time is directly proportional to work, the proportionality constant is known as Efficiency.

Q. How can I score well in Time & Work topic?

Ans: Clear your basic concepts of Time and Work and practice as many questions as you can to score well on this topic.

Q. What is the weightage of Time and Work in different Government Exams?

Ans: Usually 5-10% of questions are asked about this topic in different competitive exams.

Time and Work Notes, Simple Tricks To Solve Questions_60.1

You May Also Read this:

FAQs

How do you calculate time and work problems?

You can easily solve the time and work problems by finding the relation between quantities and using the formula and short tricks given.

What is the formula for time and work?

Time= Work done/Efficiency is the formula for time and work.

How do you solve time and work problems quickly?

To solve the problem quickly, you must first try to calculate the per day working efficiency and then solve the question.

Download your free content now!

Congratulations!

Time and Work Notes, Simple Tricks To Solve Questions_80.1

General Awareness & Science Capsule PDF

Download your free content now!

We have already received your details!

Time and Work Notes, Simple Tricks To Solve Questions_90.1

Please click download to receive Adda247's premium content on your email ID

Incorrect details? Fill the form again here

General Awareness & Science Capsule PDF

Thank You, Your details have been submitted we will get back to you.

Leave a comment

Your email address will not be published. Required fields are marked *